Construction Progress
Slab Update

Add Slab Update

From here the demand letter will generate.

Used to compute the GST column for every row.

Slab-wise Schedule (Plinth Work to Plumbing)

One slab per floor is auto-generated between Plinth Work and Brick Work, based on Total Floor. This section is read-only — use Update to mark a stage done and attach photo/video proof. Amounts are computed based on a per-unit-agreement value of ₹1.46 Cr.

Particulars Date Percentage (%) Amount (₹) GST (₹) Status Action
Plinth Work 15 Sep 2025 10.00 14,60,000 73,000 Done
1st Slab 23 Oct 2025 5.00 7,30,000 36,500 Done
2nd Slab 30 Nov 2025 5.00 7,30,000 36,500 Done
3rd Slab 07 Jan 2026 5.00 7,30,000 36,500 Done
4th Slab 14 Feb 2026 5.00 7,30,000 36,500 Done
5th Slab 24 Mar 2026 5.00 7,30,000 36,500 Done
6th Slab 01 May 2026 5.00 7,30,000 36,500 In Progress
7th Slab 5.00 7,30,000 36,500 Pending
8th Slab 5.00 7,30,000 36,500 Pending
9th Slab 5.00 7,30,000 36,500 Pending
10th Slab 5.00 7,30,000 36,500 Pending
11th Slab 5.00 7,30,000 36,500 Pending
12th Slab 5.00 7,30,000 36,500 Pending
Brick Work 8.00 11,68,000 58,400 Pending
Internal Plaster 6.00 8,76,000 43,800 Pending
Flooring 6.00 8,76,000 43,800 Pending
Plumbing 5.00 7,30,000 36,500 Pending