Construction Progress
Slab Update
Add Slab Update
From here the demand letter will generate.
Used to compute the GST column for every row.
Slab-wise Schedule (Plinth Work to Plumbing)
One slab per floor is auto-generated between Plinth Work and Brick Work, based on Total Floor. This section is read-only — use Update to mark a stage done and attach photo/video proof. Amounts are computed based on a per-unit-agreement value of ₹1.46 Cr.
| Particulars | Date | Percentage (%) | Amount (₹) | GST (₹) | Status | Action |
|---|---|---|---|---|---|---|
| Plinth Work | 15 Sep 2025 | 10.00 | 14,60,000 | 73,000 | Done | |
| 1st Slab | 23 Oct 2025 | 5.00 | 7,30,000 | 36,500 | Done | |
| 2nd Slab | 30 Nov 2025 | 5.00 | 7,30,000 | 36,500 | Done | |
| 3rd Slab | 07 Jan 2026 | 5.00 | 7,30,000 | 36,500 | Done | |
| 4th Slab | 14 Feb 2026 | 5.00 | 7,30,000 | 36,500 | Done | |
| 5th Slab | 24 Mar 2026 | 5.00 | 7,30,000 | 36,500 | Done | |
| 6th Slab | 01 May 2026 | 5.00 | 7,30,000 | 36,500 | In Progress | |
| 7th Slab | — | 5.00 | 7,30,000 | 36,500 | Pending | |
| 8th Slab | — | 5.00 | 7,30,000 | 36,500 | Pending | |
| 9th Slab | — | 5.00 | 7,30,000 | 36,500 | Pending | |
| 10th Slab | — | 5.00 | 7,30,000 | 36,500 | Pending | |
| 11th Slab | — | 5.00 | 7,30,000 | 36,500 | Pending | |
| 12th Slab | — | 5.00 | 7,30,000 | 36,500 | Pending | |
| Brick Work | — | 8.00 | 11,68,000 | 58,400 | Pending | |
| Internal Plaster | — | 6.00 | 8,76,000 | 43,800 | Pending | |
| Flooring | — | 6.00 | 8,76,000 | 43,800 | Pending | |
| Plumbing | — | 5.00 | 7,30,000 | 36,500 | Pending |